Project: Parkside
Client: RG Carter
Project value: £750,000
Scope of works: Full British Gypsum spec partitions and MF CasoLine ceilings, 3500m2 of Zenita DB + suspended ceilings
Start date: Early 2023
Program duration: 4 months
We are really looking forward to getting going on this project for RG Carter. The concrete core has now been built and the steel framing instal is in progress ready for us to get in and install partitions and suspended ceilings. The image above is a CGI of the finished building.